Final inspection!

July 6th, 2024

I know that I have been remiss in my updates on the consistent work that has been done these last four years on the Inner Sanctum project. My last update was in 2021. Since then, we have worked tirelessly on plumbing, electrical, sheet rock installation, mechanical operations, welding beams, installing lighting, and much more.

In the last 4 years, through concerted effort, we passed rebar inspections, concrete inspections, rough plumbing, final plumbing, rough electrical, final electrical, mechanical, structural, sheer wall, sheetrock, and more. We also went through a permit revision check to pour a concrete retaining wall. And on Thursday, June 13th, we passed our final building inspection and after 4 years, our permit was finally closed! 🎉

In order to finish this new space as a welcoming, accommodating community dungeon, we have so much more to do. What an exciting journey! It's so fun to watch a plan come to life. As always, we can use your help! Together we can build the dream. ❤️

Updates

The Permit
March 13th, 2020
The Complaint
March 26th, 2020
The Cave
April 14th, 2020
The Supports
May 1st, 2020
The Rebar
May 21st, 2020
Volunteer Work Day 1
June 7th, 2020
First Inspection
June 29th, 2020
The First Pour
July 3rd, 2020
Volunteer Work Day 2
July 12th, 2020
The Bamboo (fun video)
July 22nd, 2020
Second Inspection
August 15th, 2020
The Second Pour
September 9th, 2020
Volunteer Work Day 3
October 10th, 2020
Volunteer Work Day 4
October 11th, 2020
Volunteer Work Day 5
October 17th, 2020
Video Tour
October 18th, 2020
Volunteer Work Day 6
October 18th, 2020
More Rebar
October 23rd, 2020
The Staircase
October 29th, 2020
The Steel
December 21st, 2020
Final Pour!
March 13th, 2021
Second Entrance
June 15th, 2021
Bathroom/Wet Room
July 15th, 2021
Rain DeGrey and Shay
August 7th, 2021
Final inspection!
July 6th, 2024