I know that I have been remiss in my updates on the consistent work that has been done these last four years on the Inner Sanctum project. My last update was in 2021. Since then, we have worked tirelessly on plumbing, electrical, sheet rock installation, mechanical operations, welding beams, installing lighting, and much more.
In the last 4 years, through concerted effort, we passed rebar inspections, concrete inspections, rough plumbing, final plumbing, rough electrical, final electrical, mechanical, structural, sheer wall, sheetrock, and more. We also went through a permit revision check to pour a concrete retaining wall. And on Thursday, June 13th, we passed our final building inspection and after 4 years, our permit was finally closed! 🎉
In order to finish this new space as a welcoming, accommodating community dungeon, we have so much more to do. What an exciting journey! It's so fun to watch a plan come to life. As always, we can use your help! Together we can build the dream. ❤️