Inner Sanctum will have two entrances, one from the side and one from the back. Both require a concrete pour for the stairs. We've completed the pour for one entrance and are getting ready for the second pour for the other entrance. Two areas of egress are important for fire safety. Each entrance area also has to have its own drainage system in case of severe rain so our new dungeon basement does not get flooded! Drains are connected to a sump pump and buried under gravel.

Updates

The Permit
March 13th, 2020
The Complaint
March 26th, 2020
The Cave
April 14th, 2020
The Supports
May 1st, 2020
The Rebar
May 21st, 2020
Volunteer Work Day 1
June 7th, 2020
First Inspection
June 29th, 2020
The First Pour
July 3rd, 2020
Volunteer Work Day 2
July 12th, 2020
The Bamboo (fun video)
July 22nd, 2020
Second Inspection
August 15th, 2020
The Second Pour
September 9th, 2020
Volunteer Work Day 3
October 10th, 2020
Volunteer Work Day 4
October 11th, 2020
Volunteer Work Day 5
October 17th, 2020
Video Tour
October 18th, 2020
Volunteer Work Day 6
October 18th, 2020
More Rebar
October 23rd, 2020
The Staircase
October 29th, 2020
The Steel
December 21st, 2020
Final Pour!
March 13th, 2021
Second Entrance
June 15th, 2021
Bathroom/Wet Room
July 15th, 2021
Rain DeGrey and Shay
August 7th, 2021
Final inspection!