Volunteer Work Day 3

October 10th, 2020

The third volunteer work day was a continuation of the first and second work day. In addition to running new wire from Inner Sanctum and up into Black Thorn, we now also had the task of taking down all the closed cell rigid polyurethane foam insulation that covered up additional fiberglass foam from inside the bays between the ceiling joists of the basement.

The reason for removing the rigid foam insulation was not only to facilitate the re-wiring project but to also prepare to re-run water and gas lines for Black Thorn. Those old plumbing lines, like the electrical wire, hung down in disarray and at disjointed angels from the first floor of Black Thorn and needed to be moved out of sight, tucked neatly behind sheet rock in preparation to cap the ceiling of Inner Sanctum. The amount of insulation to take down was daunting but we had the man power to do it.





Updates

The Permit
March 13th, 2020
The Complaint
March 26th, 2020
The Cave
April 14th, 2020
The Supports
May 1st, 2020
The Rebar
May 21st, 2020
Volunteer Work Day 1
June 7th, 2020
First Inspection
June 29th, 2020
The First Pour
July 3rd, 2020
Volunteer Work Day 2
July 12th, 2020
The Bamboo (fun video)
July 22nd, 2020
Second Inspection
August 15th, 2020
The Second Pour
September 9th, 2020
Volunteer Work Day 3
October 10th, 2020
Volunteer Work Day 4
October 11th, 2020
Volunteer Work Day 5
October 17th, 2020
Video Tour
October 18th, 2020
Volunteer Work Day 6
October 18th, 2020
More Rebar
October 23rd, 2020
The Staircase
October 29th, 2020
The Steel
December 21st, 2020
Final Pour!
March 13th, 2021
Second Entrance
June 15th, 2021
Bathroom/Wet Room
July 15th, 2021
Rain DeGrey and Shay
August 7th, 2021
Final inspection!
July 6th, 2024